How long does a full renovation of a flat take in Barcelona?

A full renovation of a flat in Barcelona takes about three to four months (90–120 days) from the first day of works to handover, based on the flats we renovate. That excludes the permit: about a month of paperwork, plus any council wait for your route.

You want a date: when the builders leave, when you can move in, when the flat can go on the market. Plan around the wrong figure and you pay for it, in rent or in a sale that slips. We draw up the project and run the site on every flat we renovate, so these figures come from our own jobs.

Most of the uncertainty sits in the permit, and it turns on one question: are you moving any walls?

How long does a full renovation of a flat take?

Three to four months is the time we plan for a full flat renovation in Barcelona: 90 to 120 days of works, from the first day on site to handover. Preparing and obtaining the works permit happens before that and isn’t counted.

That figure comes from our experience renovating flats in Barcelona, both for private clients and on flats we buy ourselves.

We leave the permit out of it on purpose: preparing the paperwork takes us about a month and the council’s wait after that depends on the route your works need, and you’ll find both in the permit section below.

Why a range rather than one date? We quote 90 to 120 days to leave room for unforeseen issues and for changes made along the way.

Can a full renovation be done in two months?

Finishing a full renovation in two months depends on every decision being made before works start. On flats we buy and renovate ourselves, that’s the case, and we usually finish in about two months when nothing changes. With private clients, we plan on three to four.

On our own flats, the layout, materials and finishes are fixed from day one. Nobody changes their mind halfway, so works keep moving from one stage to the next.

Private clients make decisions as they see the flat take shape. That’s normal.

It’s also why we plan for three to four months, rather than promise two. If you want to get closer to two, settle the layout, the kitchen, the bathroom and the finishes before works begin, and stick with them.

What delays a renovation most?

Changes a client asks for after works have started cause the most delay in a full renovation, based on our projects in Barcelona. Our architect and our director both named them as the main reason works run beyond plan.

A change can mean redoing work that’s already finished. It can also mean pausing while a new decision is made.

Either way, the days add up quickly. The fix is simple, though not always easy: make your decisions before works start, and keep them.

How long does a kitchen or bathroom renovation take?

A kitchen or bathroom renovation takes about two to three weeks, based on our recent projects in Barcelona. That’s the time on site for one room renovated on its own, compared with three to four months for a full renovation of the flat.

Inside a full renovation, the kitchen and bathroom are part of the three to four months, not extra time on top.

On their own, they’re a much shorter job. If you’re preparing to sell, a kitchen or bathroom alone is often the quicker route; we come back to that in the section on selling.

What are the stages of a full renovation?

Every full renovation we quote follows the same order of trades:

  1. Project and permit

  2. Demolition and clearance

  3. Installations: electrics, plumbing, heating and air-con

  4. Floors, walls and ceilings

  5. Carpentry and windows

  6. Painting

  7. Handover

We don’t put a duration on each stage. The figure that matters is the total, and in our experience, that’s three to four months of works.

Each stage is also a line in our quotes, so the order doubles as a cost breakdown. You’ll find typical figures for each in our guide to how much a full renovation of a 70 m² flat costs.

What comes first in a full renovation?

The project and the works permit come first in a full renovation. Our architect draws up the project, then we file it with Barcelona City Council under the permit route the works need. Demolition, the first work on site, starts only once that route allows it.

The project is where the decisions that drive your timeline get made. These include the layout, the installations, the kitchen, the bathroom and the finishes.

Settle them here, and the works that follow have nothing to wait for.

The project also decides the permit – whether you move walls or touch the structure sets which route applies. That, in turn, sets how soon works can start.

How long does a works permit take in Barcelona?

A works permit in Barcelona takes about a month to prepare and file, in our experience. The wait after filing depends on the route: none for a notification or immediate communication, up to a month for a deferred communication, and two to three months for a major licence.

Our part takes about a month: roughly two weeks to draw up the project and two to file it. That’s based on the permits we handle for the flats we renovate.

What happens next depends on whether the works change the layout, the structure or the façade.

Barcelona permit routes for renovating a flat

What the works involve and permit routes

  • No change to layout, structure or façade, in a building that isn’t listed or protected

    • Permit route: Notification (assabentat)

    • When works can start: The day after notifying the council

    • Time allowed to carry out the works: Three months

  • Layout changes without touching the structure, or touching it only at isolated points

    • Permit route: Immediate works communication (type II)

    • When works can start: The day after filing, once the documents are verified and the provisional construction tax is paid

    • Time allowed to carry out the works: Six months

  • Work that partly affects the structure, or renovating two or more flats in the same building

    • Permit route: Deferred works communication (type I)

    • When works can start: Once the council's review period (up to one month) has passed and the construction tax is paid

    • Time allowed to carry out the works: Six months

  • Global structural work, new dwellings or a change of use

    • Permit route: Major works licence

    • When works can start: Once granted (the council has two months to decide, three where fire or heritage reports are needed)

    • Time allowed to carry out the works: Start within one year, finish within three

Source: Barcelona’s works ordinance (ORPIMO), consolidated 2022.

Types I and II also need a declaration from the technician and a technical suitability report as part of the filing.

Whichever route applies, the construction tax is paid before works start. We set out what it adds in our breakdown of renovation costs for a 70 m² flat.

These routes are Barcelona’s; other cities, Madrid included, handle works permits differently.

For the official requirements, see Barcelona City Council’s page on works permits.

Can works start straight away if you don’t move any walls?

Works can start the day after you notify Barcelona City Council if they don’t change the layout, structure or façade and the building isn’t listed or protected. This notification, called an assabentat, needs no documents; the works must be finished within three months.

It suits works that leave every room where it is.

The three-month limit is the catch. If your works might run longer, or the scope grows to include moving walls, the notification no longer covers them.

Check the building’s status first. If it’s listed or protected, a notification isn’t available, even for the same works.

Do you need a major works licence to move walls in Barcelona?

A major works licence in Barcelona is needed only for global structural work, new dwellings or a change of use. Moving walls without touching the structure, or touching it only at isolated points, needs an immediate works communication. Partial structural work needs a deferred communication.

Knocking through a partition wall to open the kitchen onto the living room is a layout change; it goes through a communication, not a licence.

That difference matters for your timeline: an immediate communication lets works start the day after filing, once the documents are verified and the tax is paid; a major works licence means waiting for the council’s decision, which it has two months to make.

The project decides which route applies; we make that call when we draw it up, based on exactly what the works change.

How does a renovation affect when you can sell?

Renovating before you sell puts roughly four to six months between starting the permit and listing your flat in Barcelona, as a rough guide. That adds about a month of permit paperwork, up to a month’s council wait and three to four months of works.

Those figures cover works filed as an immediate (type II) or deferred (type I) communication.

The sum breaks down like this:

  • About one month to prepare and file the permit, in our experience.

  • Plus the route’s wait: none for type II, one month for type I.

  • Plus three to four months of works.

That’s roughly four to five months with type II, or five to six with type I, before the flat is ready to list. Treat it as a rough guide built from these figures, not a promise.

Then comes the sale itself; we look at that separately in how long it takes to sell a flat in Barcelona.

If you need to sell sooner, renovating may not be the right move at all – we can buy your flat in Barcelona as it is, without the works.

Is it quicker to make targeted updates before selling?

Targeted updates are quicker than a full renovation before selling: a kitchen or bathroom takes about two to three weeks, in our experience. Where the layout, structure and façade stay as they are, a notification to Barcelona City Council is enough and works can start the next day.

Targeted, visible updates are also what we usually recommend before selling. In our experience, buyers notice the floors, the kitchen and the bathroom first.

A full renovation still makes sense when a flat is in poor condition; an inherited flat that hasn’t been touched in decades is the typical case.

Whether it pays to renovate at all before listing is a separate question; we cover it in whether to renovate before selling.

Planning a renovation, or weighing up what to do before you sell? Tell us about your flat and we’ll send a free quote and project proposal, with a realistic timeline. If you’re selling, we’ll value it for free too. 

Alba, our architect, plans every flat renovation we take on in Barcelona and runs the site herself.

Get in touch

Article published 15/11/2026

Grupo inmobiliario especializado en la zona de Barcelona

En ParkRose Properties un servicio integral y personalizado para clientes que quieren comprar, vender, alquilar o reformar un inmueble. Nuestro equipo de expertos te informará de todos nuestros servicios y responderá a todas tus dudas.

Informate hoy